Bonham Road Paving

Bonham Road Updates

June 14, 2024

The thermoplastic paint markings have been installed.  This project is now complete. 

May 10, 2024

The roadway was resurfaced last fall; however, the final thermoplastic paint markings were not installed due to cold weather.  These paint markings will be installed soon.

March 28, 2024

The roadway was resurfaced last fall; however, the final thermoplastic paint markings were not installed due to cold weather.  The paint markings will be completed this spring.

November 1, 2023

This project is complete with the exception of the thermoplastic pavement markings.  As stated above, this work requires 50 degree temperatures.

July 7, 2023

Work is scheduled to be done in August.