Compton Road Rehabilitation & New Sidewalk
Compton Road Updates
November 1, 2023
The remaining surface paving is scheduled for Thursday or Friday. Once that is complete the only remaining item will be the thermoplastic pavement markings. These require 50 degree temperatures so it’s possible this work may need to carry over to the spring. If the decision is made to postpone until spring, the contractor will put down standard paint for the winter. The radar controlled stop signs will be installed when the full pavement markings are completed.
August 4, 2023
Sidewalk, driveways, and curb repairs from Poage Farm Rd. to the east corp line will be completed by August 18, 2023 at which time Compton Rd. will be open to traffic (to Hilltop Lane) until paving work starts in October. Work will start on the segment between Hilltop Ln. and the west corp limits on Monday, August 21, 2023. This section of Compton will be closed to thru traffic at that time.
July 9, 2023
Sidewalk and driveway work is mostly completed from Poage Farm Rd. to Ardon Lane. The fence company was on site this week to start the fence work around the retaining wall.
June 5, 2023
Sidewalk construction will begin June 5 at the Poage Farm intersection and proceed toward Mt. Pleasant Ave. This work is expected to take several weeks. The road will continue to be closed to thru traffic for the summer and additional road closures/barricades at specific work zones may be required as well where sight distance prevents safe passage of 2 way traffic in the work zone.
May 22, 2023
Trees have been cleared and retaining wall work will be completed this week. No work is planned for next week (May 29-June 2). Sidewalk construction will begin June 5 at the Poage Farm intersection and proceed toward Mt. Pleasant Avenue. This work is expected to take several weeks. The road will continue to be closed to thru traffic for the summer and additional road closures/barricades at specific work zones may be required as well where sight distance prevents safe passage of 2-way traffic in the work zone.
April 17, 2023
Work is ongoing to clear the trees in the area of the proposed sidewalk. Duke Energy is relocating a few utility poles that are in conflict with the proposed sidewalk. The City and the contractor have come to an agreement to close Compton Road during work hours to increase worker and motorist safety as well as provide efficiencies during construction. Work on the sections of the retaining wall required for the sidewalk will begin within the next few weeks.
February 02, 2023
Bids were opened on 2/7/23. Fred A. Nemann Company was the low bidder, a contract will be awarded at the February 21, 2023, City Council meeting. Work is anticipated to begin in April/May 2023. Final paving is expected to be completed in late fall of 2023.
January 1, 2023
The project will be bid in January 2023 with construction slated to start in early spring 2023 and be completed by early fall 2023.
June 30, 2022
Most of the survey work has been completed. Designing will continue with the intent to bid on the project in late 2022 with construction beginning in the spring of 2023.
Project Details
- Re-surface all of Compton Rd. within Wyoming with some full-depth replacement.
- New sidewalks on the south side of Compton Road from the west corporation line to Mt. Pleasant Ave.
- Click here to view the preliminary sidewalk layout for Compton Rd.
- The project will be bid in January 2023 with construction slated to start in early spring 2023 and completed by early fall in 2023.
- A pre-construction meeting will be held and residents will be notified and invited to attend.
- A Public Information Meeting was held with residents on March 21, 2023, to share the specifics of the project.
Financial Impact | Year | Amount |
---|---|---|
Design and Engineering | 2022 | $114,000 |
Construction | 2023 | $1,433,300 |
Total Expense: | N/A | $1,547,300 |
Municipal Road Fund Grant | N/A | $100,000 |
SORTA Infrastructure Grant | N/A | $1,003,310 |
Grant Total | N/A | 1,103,310 |
Expenses from Capital Improvement Fund | Approved by City Council in the 2022 budget | $443,990 |
Email Rusty Herzog or call on 513-842-1382 in case you have any queries!